Project Description

This project renovates and replaces the existing playground in South Gunner’s Branch Local Park, located at 12919 Praire Knoll Court, Germantown, MD.

Background

This project will occur in two phases: improvements to the playground will happen first, followed by accessibility improvements to bring the park in compliance with the Americans with Disabilities Act (ADA). The first phase will remove the 4,000 square foot playground and replace it with a completely new playground. The concept of the new playground is to utilize net structures to maximize visibility to and through the playground without diminishing play value. The new playground will include equipment to meet the needs of children from ages 2 to 12 and will incorporate universally accessible equipment to include children of all abilities.. A small raingarden will also be constructed to treat runoff from the playground.

The second phase will reinforce the retaining walls that separate the playground from the parking lot. The path that wraps around the retaining wall will be reconstructed and handrails will be added to provide an ADA-compliant ramp to the playground. The accessible parking spaces will be shifted to the opposite side of the parking lot and a new connection will be built to connect to the parking spaces to the ramp.

Status/Project Update

This project is currently in concept design. Please review the playground plans and images of the play components. Please contact Aaron Feldman at 301-650-2887 or Aaron.Feldman@MontgomeryParks.org with comments or questions.

Calendar and Meeting Notes

Links to review meeting notes and presentation materials will be attached to each applicable calendar event as it is scheduled and completed.

DATE/TIME
DISCUSSION AND MEETING NOTES
LOCATION
Spring 2016 Concept design and public comments
Summer/Fall 2016 Develop construction documents
Winter 2016/2017 Construct Phase I
Future Construct Phase II – (date not yet available)

 