Ayrlawn Local Park – Accessibility Improvements

Project Description

In accordance with ADA requirements, Montgomery Parks is proposing to install various upgrades to improve accessibility to various amenities within the park.  The upgrades will consist primarily of new parking spaces, walkways and support features. Additionally, Montgomery Parks will install drainage improvements to minimize the flooding and pooling of water in the area near the playground. The installation and completion of all improvements began in the summer of 2015 and will be completed in the summer of 2016.

Background

In accordance with Montgomery Parks Settlement Agreement with the US Department of Justice, improvements to various amenities within the park are required to be performed.

A community meeting was held on April 14, 2015 to review and discuss the proposed plans for improvement. One outcome of the meeting was that Montgomery Parks review additional options for access, as well as to further coordinate with Montgomery County Government on possible upgrades to the property leased to the YMCA by Montgomery County Government. A second community meeting was held July 28th in which various options were outlined and discussed. The scope of the improvements for Phase 2 was accepted by the community.

The proposed improvements at/near softball Field # 2, Phase 1, were accepted by the community and construction commenced during 2015.

Phase 2 improvements will consist of the addition of several new regular parking spaces and an accessible space in front of the YMCA, a new ramp/entrance into the YMCA, a walkway extension from the upgraded parking lot to various amenities such as the playground and tennis courts, and stormwater management/drainage upgrades consisting of a bio-swale and piping. Improvements to water quality and a reduction in ponded water in/near the playground are expected.

Status/Project Update

Phase 1 construction is currently underway and should be completed in the spring of 2016. Construction of the remaining improvements are scheduled to begin during the spring of 2016.

Calendar and Meeting Notes

Links to review meeting notes and Planning Board memos will be attached to each applicable calendar event as it is scheduled and completed.

DATE/TIME
DISCUSSION AND MEETING NOTES
LOCATION
April 14, 2015
7pm – 9pm
Community Meeting #1 – Staff discusses the proposed ADA improvement plans and solicit community input
– Meeting minutes
YMCA Ayrlawn Program Center
5650 Oakmont Avenue
Bethesda, MD 20817
June 2015 Phase 1 ADA improvements began
July 28, 2015
7pm – 9pm
Community Meeting #2 – To review the incorporated recommendations made by the community at the previous meeting
– Topics for discussion
– Options 1 – 6 graphic presented
YMCA Ayrlawn Program Center
5650 Oakmont Avenue
Bethesda, MD 20817
Spring 2016 – Phase 1 improvements complete
– Phase 2 improvements to begin
Summer 2016 – Phase 2 improvements complete

M-NCPPC Project Contact

Bob Green, Senior ADA Compliance Project Manager
Bob.Green@MontgomeryParks.org
Phone: 301-495-2571

Bookmark and Share
Last Updated: August 30, 2016