Rock Creek Trail Pedestrian Bridge

Division: Park Development

Program Cover Rock Creek Trail Pedestrian Bridge Pedestrians on bridge. Completed bridge

Click thumbnails for larger views 

Description

Rock Creek Regional Park
This project provides a new pedestrian bridge that will be a grade separated safe crossing for the Rock Creek Hiker-Biker Trail over Veirs Mill Road and removes the need for an existing on-road segment of the trail. This project also provides the local residents of the Aspen Hill community a safe crossing of heavily travelled Veirs Mill Road to access bus transit or other destinations.

Background

The popular Rock Creek Hiker-Biker Trail extends 15 miles from Beach Drive at the District of Columbia line to Lake Needwood in Rock Creek Regional Park.  The trail currently crosses Veirs Mill Road at grade at a signalized at Aspen Hill Road.  To the north of Veirs Mill Road, the trail is on-road for approximately 0.2 miles traversing Aspen Hill Road, Adrian Street, Baltic Avenue, and finally the access drive to Aspen Hill Local Park before continuing northward as a trail.  Pedestrian improvements at this intersection were recommended in the 1998 Countywide Park Trails Plan and were recommended by the Montgomery County Council in 2001.

A facility planning study was conducted and a plan for this project was approved by the Montgomery County Planning Board on September 11, 2003.  For this project, the Commission obtained Federal Transportation Enhancement funds and a Maryland Program Open Space grant, in the total amount of $5.327M. The project was approved and funded for detailed design and construction by the Montgomery County Council.  Detailed design was completed and the project was advertised for construction in April 2008.

Status/Project Update

Construction of the project is complete. The bridge and approach trail are open for use by the public.

Calendar and Meeting Notes

Links to review meeting notes and Planning Board memos will be attached to each applicable calendar event as it is scheduled and completed.

DATE/TIME
DISCUSSION AND MEETING NOTES
LOCATION
September 11, 2003 Planning Board Meeting – Facility Plan approved Montgomery Regional Office Auditorium
8787 Georgia Avenue
Silver Spring, MD 20910
January 2005 Design begins
April 2008 Design completed
December 2008 Construction begins
Spring 2011 Construction completed and bridge opens
July 23, 2011
10:00am – 12 noon
Grand Opening Celebration (on location at bridge) Parking availible at:
Aspen Hill Local Park
5013 Baltic Avenue
Aspen Hill, MD 20853

M-NCPPC Staff Contact

Kris Krishnamurthy, Construction Manager
Kandikere.Krishnamurthy@MontgomeryParks.org
301-495-2593

Last Updated: July 18, 2017