Pinecrest Local Park – Renovation and ADA Modifications

Division: Park Development
Bookmark and Share

Pinecrest Local Park aerial map   plan
Click on thumbnails for larger views


Project Description

The Pinecrest Local Park is located in the Woodmoor section of Silver Spring, 301 St. Lawrence Drive, Silver Spring, MD 20901.  Existing park amenities include a soccer/softball field, tennis courts, playground, park activity building, and parking lot.

The goal of this project is to provide necessary site improvements and modifications for drainage and erosion control; stormwater management; accessibility compliance; connectivity to the surrounding neighborhood and school; and a safe, functional, barrier-free, and experientially pleasant circulation path/trail around the field area.  The circulation path/trail will be accessible and will meet the spirit and intent of the Americans with Disabilities Act (ADA) and the Architectural Barriers Act Accessibility Guidelines for Outdoor Developed Areas (ABA Outdoor Guidelines) as established by the US Access Board.  The design process will focus on incorporating principles of sustainable site design and low impact development.

A Concept Plan prepared by staff was used to develop the necessary elements for the Program of Requirements, including a concept Site Plan; Stormwater Management Concept plan; preliminary cost estimate; and determination of regulatory feasibility, which will be presented to the public to provide input on planned renovations.

  • Reconfiguring/re-grading of the soccer/softball field and surrounding area to better utilize the available space and improve field drainage conditions;
  • Correcting existing erosion problems;
  • Providing stormwater management retrofits as practical for existing facilities (there is currently no stormwater management onsite);
  • Providing stormwater management as required for new facilities;
  • Creating an asphalt path for circulation around the field that connects to existing pavement stubs at Branch Drive, Cherry Tree Lane, the parking lot, and a sidewalk from Pine Crest Elementary School; and
  • Retrofitting access to existing facilities to comply with the ADA.

Background

This 5.6-acre tract of land with mature trees and open space is adjacent to Pinecrest Elementary school and was acquired by the Maryland-National Capital Park and Planning Commission (M-NCPPC) in 1944.  It was developed into a park in the 1950’s and is home to the Pinecrest Recreation Building.

Items that were identified in prior public forums along with concerns of Parks staff, was the basis of the 15% design concept modificationsthree sheets which includes a concept Site Plan; Stormwater Management Concept plan; preliminary budgetary cost estimate; and determination of regulatory feasibility.

Status/Project Update

  • Project advertised for bid to contractors listed on Parks’ Job Order Contract list October 2, 2017
  • Two (2) Bids received November 2, 2017
  • Bids evaluated and no apparent low bidder selected due to all bids received exceeded the construction budget
  • Project postponed and cancellation of project letter sent out November 28, 2017 to all bidders
  • Re-bid project to the general public
  • Issuance of Notice To Proceed and new construction start date anticipated for Fall 2018
  • Park closed Fall 2018 through Fall 2019.  (Note: Based on status of construction, portions of the park may re-open at separate times prior to Fall 2019)

Calendar and Meeting Notes

Opportunities for public participation are shown below. Links to review meeting notes and Planning Board memos will be attached to each applicable calendar event as it is scheduled and completed.

DATE/TIME DISCUSSION AND MEETING NOTES LOCATION
April 30,2015 Design Kick-Off Meeting held to discuss:
-Development of design & construction documents
Parkside Headquarter
9500 Brunett Avenue
Silver Spring, MD 20901
June 8, 2015 Development of preliminary concept plan – 15% design
June 23, 2015

7pm – 9pm

Community Meeting #1 – To solicit community input on planned renovations
-View the presentation (12.1mb)-Meeting minutes
Pinecrest Recreation Building
301 St. Lawrence Drive
Silver Spring, MD 20901
Late Summer/Early Fall 2015 Plans 50% complete (4.5mb)
Winter 2015 – 2016 Plans 90% complete (3.5mb)
Summer 2016 Plans 100% complete
Summer 2017 Plans revised to include irrigation system and WSSC connection
October 2, 2017 Solicit bids
November 2, 2017 Bids opened and evaluated
November 28, 2017 Bids exceeded budget
-Project cancellation notice sent
April 20, 2018 Re-solicit bids for construction
Early Fall 2018 Issue notice to proceed and start construction
Fall 2019 Park re-opens

M-NCPPC Staff Contacts:

Butch Payton, Project Manager
William.Payton@MontgomeryParks.org
301-495-3587

Last Updated: September 11, 2018