Battery Lane Urban Park – Playground Renovation

Division: Park Development
Bookmark and Share

Project Description

This project provides a renovated playground for Battery Lane Urban Park.  The project will identify opportunities to maximize play for multiple age groups and to provide a safe and accessible facility.

Background

In 2009, the Montgomery County Planning Board approved the Battery Lane Urban Park Facility Plan.  The Facility Plan included the recommendation to fully renovate the existing playground area.

Status/Project Update

The Parks Department is currently in the process of finalizing construction documents and obtaining final construction permits for the renovation of the playground area.  Construction is expected to begin this Summer 2018.  The construction schedule will be posted to the website below once it has been developed.

Calendar and Meeting Notes

Links to review meeting notes and documents will be attached to each applicable calendar event as it is scheduled and completed.

DATE TIME
DISCUSSION AND MEETING NOTES
LOCATION

Fall 2016

– Playground renovation project begins.
– Assess existing site conditions and determine project needs

January 31, 2017

Community Meeting to solicit community input on the existing use of the playground and potential improvement ideas
– View the PowerPoint presentation
– View the meeting notes
– View the results from the Red Dot/Green Dot exercise
(Green dots = “Prefer”; Red dot = “Do not prefer”)
Bethesda-Chevy Chase Regional Service Center
4805 Edgemoor Lane
Bethesda, MD 20814

Spring – Fall 2017

– Develop playground design, based on community and staff feedback.
– Apply for preliminary permits

December 2017

Community Review of the proposed playground design
– View proposed playground design
– Provide comments by emailing or calling the Project Manager (contact information below)
– Comments accepted through Friday, January 26, 2018

Winter/Spring 2018

– Develop final construction documents
– Obtain permits

Summer 2018

 Construction of playground area begins


M-NCPPC Staff Contact

Lucas Bonney, Project Manager
Lucas.Bonney@MontgomeryParks.org
(301) 495-2572

Last Updated: May 22, 2018