Project Description

This project provides a renovated playground for Battery Lane Urban Park.  The project will identify opportunities to maximize play for multiple age groups and to provide a safe and accessible facility.

Background

In 2009, the Montgomery County Planning Board approved the Battery Lane Urban Park Facility Plan.  The Facility Plan included the recommendation to fully renovate the existing playground area.

Status/Project Update

Construction of park improvements at Battery Lane Park is now complete and the park is open.  Parks Staff has installed fencing along pathways to limit access through the lawn areas that are still under renovation. This temporary fencing will remain in place until the Fall season. Please continue to use caution.

Calendar and Meeting Notes

Links to review meeting notes and documents will be attached to each applicable calendar event as it is scheduled and completed.

DATE/TIME DISCUSSION AND MEETING NOTES LOCATION
Fall 2016 – Playground renovation project begins.
– Assess existing site conditions and determine project needs
January 31, 2017 Community Meeting to solicit community input on the existing use of the playground and potential improvement ideas

– View the PowerPoint presentation
– View the meeting notes
– View the results from the Red Dot/Green Dot exercise
(Green dots = “Prefer”; Red dot = “Do not prefer”)

Bethesda-Chevy Chase Regional Service Center
4805 Edgemoor Lane
Bethesda, MD 20814“`
Spring/Fall 2017 – Develop playground design, based on community and staff feedback.
– Apply for preliminary permits
December 2017 Community Review of the proposed playground design
– View proposed playground design
– Provide comments by emailing or calling the Project Manager (contact information below)
– Comments accepted through Friday, January 26, 2018
Winter/Summer 2018 – Develop final construction documents and obtain final permits
Late Fall 2018  Construction of park improvements begins.  Click the link to view the Trail Detour Map
July 2019 Project complete.

Park re-opened

M-NCPPC Staff Contacts

David Linton, Construction Manager
David.Linton@MontgomeryParks.org
(301) 495-2597

Lucas Bonney, Project Manager
Lucas.Bonney@MontgomeryParks.org
(301) 495-2572

Last Updated: July 29, 2019