Centerway Local Park – Playground Renovation

Division: Park Development
Bookmark and Share
structure Playground at Centerway Local Park

Click image to enlarge


Project Description

This project will renovate the existing playground and enhance the accessibility of the picnic shelter and parking lot at Centerway Local Park. The Park is located at 9551 Centerway Road, Gaithersburg, MD.

Background

The existing playground will be removed and a new playground will be installed in its place. Local park playgrounds are typically 3,500 to 5,000 square feet in size and include playground equipment to meet the needs of children from ages 2 to 12, and seating for caregivers. Typical types of equipment include swings, play structures, and smaller freestanding pieces.

Enhancements to the parking lot include improved ADA spaces with access to the picnic shelter, the playground, and the ballfield.  The existing picnic shelter will be replaced, the surfacing will be leveled, and improved and accessible furnishings will be added.

Status/Project Update

  • A virtual community meeting was held on Tuesday, September 15th, 2020 at 7:00pm to discuss the project and gather input from the community.
  • Community members can now provide input on the project by completing the survey on the project’s Open Town Hall page. The survey will close on October 31, 2020.

Calendar and Meeting Notes

Links to review meeting notes and presentations will be attached to each applicable calendar event as it is scheduled and completed.

 

DATES EVENTS LOCATIONS
Fall 2020 Planning
Tuesday, September 15, 2020 A virtual community meeting was held.

September 15 – October 31, 2020 Community members are invited to provide input on the project  by visiting Open Town Hall
Winter 2020/Spring 2021
Develop design concepts
Spring 2021
Public review of design concepts
Summer 2021 Design
Finalize design and draft construction documents
Spring 2022 Construction
Begin construction.

* Date and time subject to change. Please confirm the schedule on the Montgomery Planning Board Agenda webpage closer to the date.

M-NCPPC Staff Contact

John Whilden, Project Manager

John.Whilden@montgomeryparks.org

(301) 495-2595

Last Updated: October 23, 2020