Project Description

This project refines recommendations for the propagation and maintenance area at Brookside Gardens and develops a concept plan to facilitate construction of a new growing greenhouse within the maintenance area located at 12315 Fernmont Lane in Wheaton Regional Park.  These improvements will provide improved, consolidated plant growing space for the gardens.

Background

A Master Plan for Brookside Gardens was completed and approved by the Montgomery County Planning Board in March 2005, providing a long-term vision for renewal of the Gardens. The master plan proposed that the propagation and maintenance area be reconfigured to consolidate functions and expand the office, storage and growing space.

This project reviewed the master plan recommendations for the propagation and maintenance area and proposes to refine the master plan to better utilize existing structures that are currently in good condition and allow for improvements to be made in phases over time as funding becomes available.  In addition, the project includes a concept plan for a new growing greenhouse and associated improvements, which are proposed as a first phase for the implementation of improvements to the maintenance area.

Status/Project Update

The project consultant is currently making revisions to the project schedule. Once the revisions are complete, the schedule will be posted below.

Calendar and Meeting Notes

Links to review meeting notes and Planning Board memos will be attached to each applicable calendar event as it is scheduled and completed.

DATE TIME
DISCUSSION AND MEETING NOTES
LOCATION
April 24, 2013 Community Meeting – To discuss proposed refinements to the Master Plan, as well as a concept plan to install a new greenhouse Brookside Gardens Visitors Center
Auditorium
1800 Glenallan Avenue
Wheaton, MD 20902
June 13, 2013 Planning Board Meeting – Request approval of refinements to the Master Plan, as well as the greenhouse concept plan and budget
– Approved with conditions
– View approved package (Item 4; K. Paniati) 
M-NCPPC, Montgomery Regional Office Building
Auditorium
8787 Georgia Avenue
Silver Spring, MD 20910
Fall/Winter 2015 Project schedule being revised

 

M-NCPPC Staff Contacts

Mark Buenavista, Project Manager
Mark.Buenavista@MontgomeryParks.org
301-495-2522

Last Updated: July 31, 2017