This project renovates and replaces the existing playground in John Haines Neighborhood Park, located at 25000 Oak Drive, Damascus, MD.

Background

The existing playground will be removed and a completely new playground will be installed in its place.  Local park playgrounds are typically 3,500 to 5,000 square feet in size and include playground equipment to meet the needs of children from ages 2 to 12.  Typical types of equipment include swings, play structures, and smaller freestanding pieces of equipment such as spring rockers or spinning elements.

Status/Project Update

Construction drawings for the playground are currently being developed. The final design is posted above. Click on the thumbnails for larger views.

Calendar and Meeting Notes

Schedule for the calendar is currently being developed. Links to review meeting notes and presentation materials will be attached to each applicable calendar event as it is scheduled and completed.

DATE/TIME
DISCUSSION AND MEETING NOTES
LOCATION
Spring 2013 Playground placed on renovation list  
Fall/Winter 2013-2014 Exploring areas to relocate the playground in order to meet new ADA (American with Disabilities Act) requirements - UPDATE >> The new playground will remain in the existing location. An accessible trail will be constructed.  
Spring 2014 Design phase  
Fall/Winter 2014 Design complete  
Spring 2015 Developing construction drawings  
Summer 2015 Construction begins  

 

M-NCPPC Staff Contact

Kathleen Dearstine, Project Manager